A licensed Rhode Island builder moving into development — two sites, architectural plans drawn for both, and a path to 8 new homes.
Bedrosian Homes wasn't built on borrowed credibility — it was built job by job, from scratch, starting November 2020. Here's the track record.
Krikor Bedrosian launched Bedrosian Homes LLC in November 2020 — during one of the most difficult periods for small business in recent memory — and built it into a thriving, 5-star-rated contracting operation with 100+ completed projects across Rhode Island.
From full gut renovations to insurance claim rebuilds, kitchens, bathrooms, exteriors, and basements, the breadth of work is matched by a consistent record of quality and client satisfaction. This is a builder who knows exactly what it costs to construct the projects he's proposing — because he does this work every day.
The move into multi-family development is a natural, calculated next step: use existing skills, relationships, and capital to build long-term wealth through ownership rather than labor alone.
An income-producing 2-family on 0.64 acres anchors the portfolio. It secures this request, stays in place through every phase, and its rear lot is planned for future townhomes.
Two-family built in 1922: 2,044 SF, 6 bedrooms, 2 baths and two detached garages, with both units leased. The existing loan is about 35–39% of value. The 2-family stays in place through every phase, and five new townhomes are planned for the rear of the lot.
Eight larger Manville homes sold between April and October 2026 for $550,000–$670,000, including 252 Railroad Street, directly across the street.
| Address · Lincoln RI 02838 | Price | Living SF | Lot (ac) |
|---|---|---|---|
| 43 Pearl St | $550,000 | 4,480 | 0.11 |
| 16 Manville Ave | $661,000 | 3,920 | 0.44 |
| 62 Spring St | $630,000 | 4,005 | 0.20 |
| 106 Bouvier Ave | $615,000 | 3,276 | 0.22 |
| 167 Central St | $605,000 | 4,596 | 0.32 |
| 68 Bouvier Ave | $557,000 | 3,838 | 0.11 |
| 252 Railroad St2-family · directly across the street | $616,900 | 2,064 | 0.46 |
| 1 Bouvier AveMulti-family | $670,000 | — | — |
| 245 Railroad StSubject property · 2-family · collateral | Est. $600k–$675k | 2,044 | 0.64 |
Complete drawings by National Design & Drafting — floor plans, elevations, site plans, and 3D renderings for both properties, ready for the approvals process.
An equity line of about $250,000 secured by 245 Railroad Street. It carries 511 Broad through approvals and site work to a finished foundation.
| Proposed use of funds — through foundation | Amount |
|---|---|
| Approvals: comprehensive permit, land-use counsel, application | $25,000 |
| Survey, geotechnical + structural engineering | $20,000 |
| Building permits + impact fees | $16,000 |
| Demolition of existing building, incl. abatement allowance | $35,000 |
| Clearing, excavation + grading | $20,000 |
| Foundation: poured concrete walls, footings + slabs | $70,000 |
| Utilities + site connections | $27,500 |
| 511 Broad carrying costs, about 12 months (land loan, taxes, insurance) | $30,000 |
| Reserve | $6,500 |
| Total request | $250,000 |
Three 3-story townhomes (2 bed, 2.5 bath, 1-car garage, about 1,700 SF each), priced at 2026 Rhode Island costs. Bedrosian Homes self-performs most trades, so overhead is built into the line items rather than added as an outside GC markup.
| Line item | Cost | Notes |
|---|---|---|
| Site work | $175,500 | |
| Demolition of existing ~2,450 SF building | $35,000 | Incl. asbestos survey + abatement allowance |
| Clearing, excavation, grading | $20,000 | |
| Foundation: poured concrete walls, footings, slabs | $70,000 | Poured concrete |
| Utilities + site connections | $27,500 | Water, sewer, gas, electric |
| Driveways + concrete patios × 3 | $23,000 | Patio per unit |
| Structure + envelope | $424,500 | |
| Framing — 2×6 ext / 2×4 int · 3 floors × 3 units | $192,500 | Per NDD construction spec |
| Roofing | $52,500 | Architectural shingle per elevation |
| Windows + exterior doors | $55,000 | Double-hung per plans |
| Garage doors × 3 | $10,000 | |
| Siding + exterior trim | $50,000 | Fiber cement per elevations |
| Insulation | $30,000 | Spray foam + batt |
| Rear decks × 3 | $34,500 | Stairs to grade |
| Mechanical / electrical / plumbing | $172,500 | |
| Plumbing × 3 units | $64,500 | |
| HVAC × 3 units | $52,500 | |
| Electrical × 3 units | $55,500 | |
| Interior finishes | $316,500 | |
| Drywall, tape + finish | $33,500 | All 3 units |
| Hardwood floors — 2nd + 3rd floors | $43,500 | |
| Vinyl plank — 1st floor | $11,000 | |
| Kitchens × 3 | $69,000 | Cabinets, counters, appliances |
| Bathrooms — 6 full + 3 half | $90,000 | Tile, fixtures, vanities |
| Stairs + railings | $33,000 | Interior + deck stairs |
| Interior doors, trim + paint | $30,000 | |
| Laundry hookups × 3 | $6,500 | |
| Hard costs total | $1,089,000 | ~$214 / SF |
| Contingency | $109,000 | 10% of hard costs |
| Soft costs | $82,500 | |
| Permits + impact fees | $16,000 | Building, plumbing, electrical, mechanical |
| Structural engineering | $12,000 | Plans in hand |
| Survey + geotechnical | $8,000 | |
| Comprehensive permit | $25,000 | Land-use counsel, application, RIHousing |
| Builder's risk + liability insurance | $10,000 | |
| Landscaping + final grading | $11,500 | |
| Financing + carrying costs | $99,000 | |
| Construction loan interest | $64,000 | About 14 months |
| Loan fees, appraisal, closing | $20,000 | |
| Taxes, insurance, utilities during build | $15,000 | |
| Construction total | $1,379,500 | ~$459,800 per unit |
| Land — 4 lots | $365,000 | Purchased October 2025 |
| Total project cost | $1,744,500 | ~$581,500 per unit |
Five new craftsman townhomes on the rear of the lot, with the existing 2-family kept as a rental. Plans are drawn (National Design & Drafting, Dec 2022). A detailed budget will follow once 511 Broad is underway and Lincoln approvals and unit sizes are confirmed.
A phased plan: financing and approvals now, 511 Broad next, and the Railroad Street townhomes after that.